Construction Notes
McCraith Beverages – 33,250 SF Warehouse Addition
New York Mills, New York
Executive Project Manager: David Kleps
Project Manager: Fran Barres
Superintendent: Dick Jones
This is our second project for McCraith Beverages in New York Mills. We completed a major expansion and renovation at their Saranac Lake High Peaks Beverage facility in 2014. This project in New York Mills included (2) Buildings and major site work was completed in spring of 2019.
The first phase consisted of (4) new Loading Docks with retaining walls in the original Truck Garage.
The next phase was a new 14,250 sf Truck Garage with a Drive Thru Automated Truck Way Bay.
The last phase was a 19,000 sf Warehouse addition that connected the new recycling building to the existing Warehouse. That project was completed through winter of 2019.
The major site work continued while allowing the operations to continue – it included new Power and Water Utilities to service the Truck Garage and Wash Bay, a large cut to the adjacent hill and retaining walls, new asphalt drives, concrete pads and landscaping.